BMXAA8368W Conditions are defined for tasks in the current job plan. When the job plan is applied to a work order, some tasks might not be copied to the work order if the conditions are not met. Tasks that are not copied to a work order can cause a disruption to the sequential flow of the work order. Define predecessor relationships to reduce the disruption for tasks that are not copied to the work order.

Explanation

You must define predecessor relationships to ensure that the sequential flow of a work order is not disrupted by conditions.

Action

Action